英语翻译where T = duration of construction period from the date of possession of site to substantialcompletion,in wording days,C = completed cost of project in millions of Australian dollars,adjusted to constant labor and material prices,K = a co

来源:学生作业帮助网 编辑:作业帮 时间:2024/05/13 00:31:45
英语翻译where T = duration of construction period from the date of possession of site to substantialcompletion,in wording days,C = completed cost of project in millions of Australian dollars,adjusted to constant labor and material prices,K = a co

英语翻译where T = duration of construction period from the date of possession of site to substantialcompletion,in wording days,C = completed cost of project in millions of Australian dollars,adjusted to constant labor and material prices,K = a co
英语翻译
where T = duration of construction period from the date of possession of site to substantial
completion,in wording days,C = completed cost of project in millions of Australian dollars,
adjusted to constant labor and material prices,K = a constant indicating the general level of time
performance per million Australian dollar,and B = a constant describing how the time
performance is affected by the size of the construction project measured by its cost.

英语翻译where T = duration of construction period from the date of possession of site to substantialcompletion,in wording days,C = completed cost of project in millions of Australian dollars,adjusted to constant labor and material prices,K = a co
T = 从进场之日开始直至全面竣工之日,即实际工期.
C = 工程总价,以澳元为结算货币,以百万为单位,根据长期人工和材料的价格波动进行调整.
K = 常数,表示工程期间每百万澳元的兑换水平.
B = 常数,表示工程期间受汇率影响的程度,按项目总价进行总体测算.

在T =持续时间从现场的占有日期施工期大量
完成后,在工作日,C =完成工程造价数百万美元的澳大利亚,
劳动力和原材料价格调整为常数,K =常数表示时间的一般水平
每百万澳元的性能,和B =常数描述时间
性能是由其成本衡量施工项目的大小的影响。...

全部展开

在T =持续时间从现场的占有日期施工期大量
完成后,在工作日,C =完成工程造价数百万美元的澳大利亚,
劳动力和原材料价格调整为常数,K =常数表示时间的一般水平
每百万澳元的性能,和B =常数描述时间
性能是由其成本衡量施工项目的大小的影响。

收起

其中T=从占有地盘之日起施工期间substantialcompletion,在措辞天,在数百万澳元项目C =完成成本,调整为恒定的劳动力和原材料价格上涨,K =常数,表示总水平每百万澳元timeperformance,和B=常数描述timeperformance是如何影响其成本计量的建设项目的规模

定义:
T=从工地的转移当日起到工程达到大部分完工日止,只计算工作天(不包括假日或非工作天)。
C=工程完成的成本以百万澳币元计,调整至固定人工与材料价。
K=此常数反应一般的“时间效益”,以百万澳币元为计量单位。
B=此常数描述能影响“时间效益”以工程大小的成本为计量单位。...

全部展开

定义:
T=从工地的转移当日起到工程达到大部分完工日止,只计算工作天(不包括假日或非工作天)。
C=工程完成的成本以百万澳币元计,调整至固定人工与材料价。
K=此常数反应一般的“时间效益”,以百万澳币元为计量单位。
B=此常数描述能影响“时间效益”以工程大小的成本为计量单位。

收起